Home
Products
Temporary steel bridge
Temporary steel bridge
Steel platform
Steel cofferdam
Steel sheet pile cofferdam
Steel pipe pile cofferdam
Combination of steel sheet pile and steel pipe pile cofferdam
Steel support
XT300 Truss
Tower support type A
Steel pipe and bailey beam support
Disk lock steel tubular scaffold
Preloading block
Unloading block
Traffic steel bridge
Traffic steel bridge
Bridge deck and accessories
Movable suspended scaffolding
Movable suspended scaffolding
Movable suspended scaffolding and formwork
Corbel
Construction safety products
Operation vehicle for bridge crash barrier construction
Stair
Safety barrier
Construction tools
Formwork lifting tool
Prestressed Intelligent Control Tensioning
Concrete Placing-boom
Continuous girder construction
Continuous grider construction
Solution
Design of Construction Schemes
Virtual Construction Simulation
Equipment manufacturing
Steel structure construction
Continuous grider construction
Construction machinery leasing
Projects
Construction Hanging Basket
Bracket at Block 0
Loading bridge
Temporary steel bridge B
Fabricated steel support
Steelpipe pile and assembled truss
Operation Van for Lateral Bridge Crash Barrier Construction
Stairs
R&D
R&D Centre
R&D Team
Patents
About Us
Company
News
Careers
Contact
400-0000-661
CN
Home
Products
Solution
Design of Construction Schemes
Virtual Construction Simulation
Equipment manufacturing
Steel structure construction
Continuous grider construction
Construction machinery leasing
Projects
Construction Hanging Basket
Bracket at Block 0
Loading bridge
Temporary steel bridge B
Fabricated steel support
Steelpipe pile and assembled truss
Operation Van for Lateral Bridge Crash Barrier Construction
Stairs
R&D
R&D Centre
R&D Team
Top equipment
Leading technology
Patents
About Us
Company
News
Careers
Contact
CN
Temporary steel bridge
Temporary steel bridge
Steel platform
Steel cofferdam
Steel sheet pile cofferdam
Steel pipe pile cofferdam
Combination of steel sheet pile and steel pipe pile cofferdam
Steel support
XT300 Truss
Tower support type A
Steel pipe and bailey beam support
Disk lock steel tubular scaffold
Preloading block
Unloading block
Traffic steel bridge
Traffic steel bridge
Bridge deck and accessories
Movable suspended scaffolding
Movable suspended scaffolding
Movable suspended scaffolding and formwork
Corbel
Construction safety products
Operation vehicle for bridge crash barrier construction
Stair
Safety barrier
Construction tools
Formwork lifting tool
Prestressed Intelligent Control Tensioning
Concrete Placing-boom
Continuous girder construction
Design of Construction Schemes
Continuous grider construction
Virtual Construction Simulation
Service Hotline
400-0000-661
Online Services
Corporate WeChat
沪苏湖铁路工程站前Ⅲ标
中铁十九局集团有限公司
Project Introduction
沪苏湖铁路起自上海虹桥站,途经江苏省苏州市,终至浙江省湖州市湖州站,线路全长约163.8千米。其中,沪苏湖江苏段全部落于吴江境内,全长约52.156千米,在吴江区设有苏州南(汾湖)和盛泽两个站点,预计于2024年开通运营。
Client unit
中铁十九局集团有限公司
Project scale
跨径(36+168+136+36)
Xingtu products
菱形挂篮
Project Features
独塔斜拉桥、上跨常台高速和苏嘉运河、挂篮兜底